You're currently signed in as:
User
Add TAGS to your cases to easily locate them or to build your SYLLABUS.
Please SIGN IN to use this feature.
https://www.lawyerly.ph/juris/view/c34a8?user=fbGU2WFpmaitMVEVGZ2lBVW5xZ2RVdz09
[GEORGE EDWARD KOSTER INC. v. JOSE C. ZULUETA](https://www.lawyerly.ph/juris/view/c34a8?user=fbGU2WFpmaitMVEVGZ2lBVW5xZ2RVdz09)
{case:c34a8}
Highlight text as FACTS, ISSUES, RULING, PRINCIPLES to generate case DIGESTS and REVIEWERS.
Please LOGIN use this feature.
Show printable version with highlights
99 Phil. 945

[ G.R. No. L-9305, September 25, 1956 ]

GEORGE EDWARD KOSTER INC., PLAINTIFF AND APPELLEE, VS. JOSE C. ZULUETA, DEFENDANT AND APPELLANT.

D E C I S I O N

LABRADOR, J.:

Appeal from a judgment of the Court of First Instance of Manila,  sentencing  defendant and appellant to pay plaintiff and appellee  (1)  P46,093.77, with  interest  of  6 per cent on P30,000 thereof from  September 27,  1949 and on P16,093.77 from December 8,  1949 until the amount is fully paid, (2) 20 per cent of  the full amount thereof as damages by way of attorney's fees,  and  (3)  the costs of the suit.

On June 29,  1948 plaintiff and appellee  undertook to construct for defendant and appellant the building known as the Zulueta  or  Antonio Apartments,  a four-story re-enforced concrete edifice at the north corner of Mabini and Arquiza Streets, City of Manila.  Construction  was to be in accordance with plans  and specifications prepared by Manalac Construction Co., which  acted as defendant and appellant's architects.   The owner was to furnish  the re-enforcing steel, the cement, the steel windows, and the plumbing fixtures and accessories.  The contract price was P286,755.   It was expressly agreed that should any change in the construction be agreed  upon and made, the cost of the same shall  be an addition to the contract price. Two  hundred and  fifteen  days was agreed upon  as the period for  the construction and  termination of the edifice, but that said period was to be automatically extended for delays occasioned by late deliveries  of the materials, and by fortuitous cases like, earthquakes  and bad weather.

As to acceptance, the following  terms and  conditions ,appear in the contract: 

"Article 7. Acceptance  and final payment  (a)  final  payment shall be due and  payable  ten (10)  days after the essential completion of the work provided the. work be then  fully completed and the contract  fully performed and provided  further that the  Contractor  shall have  delivered to  the  Architect  or  the  Owner  such Final Certificates as may be required by  the public  authorities. 

"The  contractor shall be under obligation to repair hidden defects and leaks in the construction which may  be discovered within six (6) months after final completion and acceptance  of the construction. 

"(b)  Upon receipt of written  notice that  the work is ready for final inspection and acceptance,  the  architect shall promptly make such inspection, and when  he finds the work acceptable  under the contract and  the contract fully performed, he shall  promptly issue a final certificate over his own signature, stating that the work provided for in this contract has been completed and is accepted by him under the terms and conditions thereof, and  that the balance found to be due the contractor except the final ten per cent (10 per cent) as noted in said final certificate,  is due and payable. 

"(c)  Before issuance of final certificate, the contractor shall submit evidence  satisfactory to the  architect that all payrolls, material bills,  and  other indebtedness connected with the  work have  been paid. 

"Should  for  any reason beyond the contractor's control or responsibility, due  to any  reasons as  set forth in. these contractual documents, the contractor be unable to supply  the final certificate of acceptance by the city authorities due to portions of the work being incomplete which are not a part of the contractor's work, then said final payment shall be  made to the contractor notwithstanding the final certificate of acceptance being not  issued: Provided, however, that the contractor shall certify to the satisfaction of the owner that all the  work,  terms and  conditions described in this contract have been performed according to specifications."  (Exhibit "A".)

The  original contract price was paid  in full and the action  seeks  to recover the additional cost of constructing  (a) a swimming pool and changes on the fourth floor, (b)  a  recreation room, and  (c)  electric wiring for the swimming poll and an additional pump Exhibits "C"  and "N").   The most important defenses  set up against the claim  are abandonment of  the  construction and delay  in its completion and failure of plaintiff and  appellee to secure a final  certificate from the public authorities, and defects in the construction, such as leaks, unevenness of the terrace filing,  cracks on the walls of the building, etc.  The trial court found that the building was completed in accordance with the contract, that the delay in completion was caused by delays in furnishing  the building materials and by additional work agreed upon by the parties  and substantial changes in the original  plan, and that the alleged defects were waived in  advance by defendant  and appellee, who had  insisted on the construction  of the  swimming pool against the advice of plaintiff, etc.

On this appeal defendant and appellant contends that there was no completion and acceptance,  as required in Article 7 of the contract, and hence plaintiff and appellant is not entitled to the payment of the amount of P46,093.77 demand in the  action.

There is no question that the work had been completed, but it is  also undisputed that  there were leaks in some parts of the edifice, same defects in the drainage,  and the contractor had  not, at  the time  of the action, delivered the final certificate from the public  authorities required of him  by the provision of the contract above  quoted.  But against these objections, we have the following facts:  (1) On September 8, 1949 the owner's  architects  made a certificate of final  acceptance as regards the  work  (Exhibit "B"); (2) there was the occupation of the edifice by the owner, without objection to the manner of the construction, and as to the absence of the certificates of inspection required of the  public authority;  (3) the  contractor had asked the owner to exempt  him from inability to secure final certificate  of acceptance  because the original  plans and specifications were  not followed and deviations from building permit plans were  made,  thus: 

"*  *  * there is still one additional subject which must be clarified and that is your  instructions to construct the building according to the plans which we estimated from and not from the plans issued by the  City Engineer's Office."  (Exhibit "FF-1")  (Underscoring ours.)

and Zulueta,  upon recommendation of his architects, expressly agreed thereto, thus: 

"In acknowledgment of your letter of  May 19, 1949, requesting me not to hold G.  E.  Koster, Inc.  for  any  civil liability due to structural  failure that may arise from the construction of the swimming  pool on the roof of my Antonjo Apartments, kindly inform Messrs. G. E. Koster, Inc., that I am expressly waiving  what ever rights the law  recognize in my favor as owner of the  newly constructed Apartment.  Be it known to them, also,  that I will hold them  responsible for any defects that may arise due to  faulty construction and for any leakage  in the swimming  pool due to faulty waterproofing."  (Exhibit "II-2")

(4) the cracks in some parts of the buildings were due to  the installation of the swimming pool in  the fourth floor, which increased the weight of the building and the load on its beams, and the leaks on the walls were caused by the  use of concrete blocks,  but the specifications did not call  for the use of waterproofing  materials and construction was according  to the specifications.   (Note that the leaks did not come from the swimming pool, which was not waived.)  The objections  against the building  were not due, therefore, to defects in the form and manner of the construction or to a faulty construction, original and as  modified, but to defects in the plans and the materials called for therein.  There is another reason for dismissing the owner's objections.  It was  expressly agreed that as to  hidden defects and leaks,  the  contractor  was to  be responsible  only for those which  may be discovered within six months after  the final acceptance of the construction. The final acceptance was made on September 8,  1949.  The action was brought  on August  29,  1950,  and  only  then did the defendant and appellant raise his objections.  The objections to  the construction must also, therefore, be considered filed  out of time and name must be overruled.

We have carefully reviewed the evidence and the analysis and appraisal thereof by his honor, the trial  judge, and we find nothing that can justify  a modification or reversal of  the trial judge's  findings and of his legal  conclusions as to the main issues involved  in the case.  But we  are not entirely in accord with his  honor in the  grant of attorney's fees as damages in favor of plaintiff and  appellee. He says: 

"The Court has, however, found that plaintiff has presented evidence to show that in filing this suit it has retained counsel whom it has agreed to pay a fee of the sum of P9,218.75, and that the filing of this case  should not  have been necessary if only the  defendant paid his just and lawful obligation"

At common law,  the successful  party usually has no right to have  the fees  of his attorney, as  such, taxed against  his opponent (14 L. ed. 181).  The court will not ordinarily allow counsel fees to the successful party Each party  to the  action must pay  his  own  lawyer * * *. Counsel fees paid in  prior action have been  allowed *  *  * (where) the conduct of the party against whom they allowed, so directly and certainly caused the expenditure for this purpose, that the loss of the amount so paid was easily within  such casual relations to  the defendant's wrong as to warrant the assessment of the damages in compensation fdr it.   (Sears vs. Inhabitants of Nahant, 102 N.  E. 491.) Our rulings before  the New  Civil Code took effect  (the present  case having arisen before)  have been as  follows: 

"It is  not sound public policy to  place a penalty on  the right to litigate.  To  compel the defeated  party  to  pay the  fees of counsel for his successful opponent would throw wide the door of temptation to the opposing party and his counsel to swell the  fees to undue proportions, and  to  apportion them arbitrarily  between those pertaining properly to one branch of the case from  the other. 

"This court has already placed  itself on record as favoring the view taken by those courts which hold that attorney's fees are not a proper element of damages."  (Tan  Ti vs. Alvear, 26  Phil.  566; The  Borden  Co. vs. Doctors Pharmaceuticals, Inc., 90 Phil., 500.) 

"* * * Counsel fees, other than  those fixed in the  rules as costs, are not an element  of recoverable damages."  (Jesswani vs. Massaram Dialdas, G. E. No. L-4651, May 12, 1952.)

We are satisfied from a review of the evidence that the refusal  of  defendant and appellant, although the case is finally decided against him, can not be said to have been caused by  mere bad faith.  The  defects in the building were proved at the trial and certainly he can not  be blamed for entertaining the  belief that they were caused by faulty construction.  To sentence him to pay plaintiff's lawyer's fees would be imposing  a penalty on his right, to litigate.   Even under the New Civil t!ode (Article 2208, par. 5) plaintiff and appellee would not be entitled to recover the fees paid to his attorney as damages, as no bad faith on the part of defendant and appellant was shown, in his refusal to pay plaintiff's claim.  The part of the judgment  sentencing  defendant  and "appellant  to pay P9.218.75 must be reversed  and defendant and appellant absolved from said demand.

Wherefore, with the modification above indicated, the judgment is hereby  affirmed, with costs against defendant and appellants.  So ordered.

Paras, C. J., Padilla, Montemayor,  Bautista,  Angelo, Concepcion, Reyes  J.  B.  L., Endencia, and Felix,  JJ., concur.

 



RESOLUTION


LABRADOR, J.:

This has reference to the motion for reconsideration filed by  defendant and appellant,  wherein claim is made that no  sufficient evidence to sustain the court's finding that the leaks and  defects of which defendant complains were due to  the modification of  the  plans by the  building of a swimming pool on the third floor, which swimming pool was not in the original plan.  It is to  be  noted  that  defendant's own  expert  witness Gregorio P. Gutierrez could not assert that the construction  and the materials were not in accordance with the specifications called for in the contract (t.s.n. pp. 233-235, Vol. IV).  On the other hand, during the, period of construction  no objection was ever registered by defendant's engineer to the manner in which the construction was being undertaken or to the materials used therein.  And when delivery was made the construction was accepted without any objection being registered at all.  Again at the ocular inspection, it was explained that the sinking of  the floor was caused by the added weight of the building caused by the addition of the swimming pool and other additions, not given in the original plans.  These are sufficient evidence to support our conclusion that the defects found were not shown to be due to faulty construction but to the  additions to the original plan.

It is to  be noted that a contractor's engagement is to build according to plans and specifications; the designs are made by the architect, and as to the sufficiency or adequacy of the structure carrying the weight of the building, the builder may not be held to account.  The foundation was designed to carry a  specified load, the building  without the swimming pool. As the owner insisted on putting additions  without a change  in  the foundation, the fault does not lie in the builder-contractor, but  in the  owner himself, and in the failure of his architect to provide the adequate foundation to take care of the new weight caused by the additions.

There is no need to consider the other ground for the reconsideration as the same is sufficiently answered  in the decision.

The motion for reconsideration is denied.  So  ordered.

Paras, C. J., Bengzon, Padilla,  Montemayor, Bautista Angelo, Concepcion, Reyes J. B. L., Endencia, and Felix, JJ., concur.


tags