This case has been cited 1 times or more.
|
2012-06-26 |
LEONARDO-DE CASTRO, J. |
||||
| Respondent PRA claims that in evaluating respondent Province's project and in issuing the necessary NTP for Phase 1 of Site 1 (2.64 hectares) of the Caticlan Jetty Port expansion and modernization, respondent PRA gave considerable weight to all pertinent issuances, especially the ECC issued by DENR-EMB RVI.[108] Respondent PRA stresses that its earlier approval of the 40-hectare reclamation project under its Resolution No. 4094, series of 2010, still requires a second level of compliance requirements from the proponent. Respondent Province could not possibly begin its reclamation works since respondent PRA had yet to issue an NTP in its favor. | |||||