You're currently signed in as:
User

MEGAWORLD GLOBUS ASIA v. DSM CONSTRUCTION

This case has been cited 4 times or more.

2009-02-27
CHICO-NAZARIO, J.
On 5 July 2000, petitioner entered into a Trade Contract with LMM Construction for partial structural and architectural works on one of its projects, the Bonifacio Ridge Condominium. According to the said Contract, petitioner had the right to withhold the retention money equivalent to 5% of the contract price for a period of one year after the completion of the project. Retention money is a portion of the contract price, set aside by the project owner, from all approved billings and retained for a certain period to guarantee the performance by the contractor of all corrective works during the defect-liability period.[4]
2008-04-30
VELASCO JR., J.
Significantly, jurisprudence teaches that mathematical computations as well as the propriety of the arbitral awards are factual determinations.[30] And just as significant is that the factual findings of the CIAC and CA--in each separate appealed decisions--practically dovetail with each other. The perceptible essential difference, at least insofar as the CIAC's Final Award and the CA Decision in CA-G.R. SP No. 86641 are concerned, rests merely on mathematical computations or adjustments of baseline amounts which the CIAC may have inadvertently utilized.
2006-12-20
TINGA, J.
Thus, in Hi-Precision Steel Center, Inc. v. Lim Kim Builders, Inc.,[24] we refused to review the findings of fact of the CIAC for the reason that petitioner was requiring the Court to go over each individual claim and counterclaim submitted by the parties in the CIAC. A review of the CIAC's findings of fact would have had the effect of "setting at naught the basic objective of a voluntary arbitration and would reduce arbitration to a largely inutile institution." Further, petitioner therein failed to show any serious error of law amounting to grave abuse of discretion resulting in lack of jurisdiction on the part of the Arbitral Tribunal, in either the methods employed or the results reached by the Arbitral Tribunal, in disposing of the detailed claims of the respective parties. In Metro Construction, Inc. v. Chatham Properties, Inc.,[25] we reviewed the findings of fact of the Court of Appeals because its findings on the issue of whether petitioner therein was in delay were contrary to the findings of the CIAC. Finally, in Megaworld Globus Asia, Inc. v. DSM Construction and Development Corporation,[26] we declined to depart from the findings of the Arbitral Tribunal considering that the computations, as well as the propriety of the awards, are unquestionably factual issues that have been discussed by the Arbitral Tribunal and affirmed by the Court of Appeals.